Venezuela

2010

  • S.S. LA ARENOSA, 765/400/230/20kV
    EDELCA
    Commissioning of SCS and protection system
  • S.S. YARACUY, 765/400/230/20kV
    EDELCA
    Commissioning of SCS and protection system

2009

  • S.S. YARACUY, 765/400/230/20kV
    EDELCA
    Commissioning leadership of the secondary systems and high voltage equipment and Commissioning of the protection system and control system
  • S.S. LA ARENOSA, 765/400/230/20kV
    EDELCA
    Commissioning of the protection system and local control system
  • S.S. TAMARE, 138/13,8kV
    ENELVEN
    Commissioning of the protection system and local control system

2006

  • S.S. S.S. 115/34,5kV FMO AND S.S. 115/34,5kV, 115/34,5kV
    CVG EDELCA
    Implementation and commissioning of data transmission system from local protections and disturbance recorders to remote control centre and training of Venezuela staff
  • S.S. S.S. 115/34,5kV FMO AND S.S. 115/34,5kV, 115/34,5kV
    CVG EDELCA
    Implementation and commissioning of data transmission system from local protections and disturbance recorders to remote control centre and training of Venezuela staff

2004

  • S.S. EDELCA/LAS CLARITAS 1, 400kV
    EDELCA
    Commissioning of centralized disturbance recording systems

2003

  • S.S. EDELCA/CARUACHI 1, 400kV
    EDELCA
    Commissioning of centralized disturbance recording systems

2002

  • S.S. EDELCA/CARUACHI, 400kV
    EDELCA
    Commissioning of the protection system and commissioning of centralized disturbance recording systems

2000

  • Two S.S. EDELCA Venezuela, 400kV
    EDELCA Venezuela
    Commissioning of centralized disturbance recording systems